Portal de San Javier

www.portaldesanjavier.com

San Javier - SpanishSan Javier - English
detail of San Javier

 

El Estacio Bridge reopens normally (25/01/2015)

Estacio bridge works as normal since last January 21 at 10: 00h.

after it has been reset signal amplifier main hydraulic pumps whose failure last December 16 prevented its opening.

The Utilities Councilman Jose Miguel Luengo reported that the bridge returns to its normal opening hours and explained that the delay in the repair was due to Made in Germany, of the necessary parts for the bridge design used German technology in its construction.

Luengo added that he has taken the opportunity for sourcing the same piece parts and other critical parts whose failure could re-let the bridge out of service before a new event, for immediate repair without having to wait for their manufacture, since there are specific pieces of which there is no stock.

Source: Ayuntamiento de San Javier

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información